1415-02 - Ord. 2015-02 - budget amendment for Safe Routes to School (part of Reso. 2015-02) - 10/14/2014 RESOLUTION NO. 201S-02
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF HUNTSVILLE,TEXAS AUTHORIZING THE
CITY MANAGER TO ENTER INTO A TENDER AGREEMENT WITH CONTINENTAL CASUALTY
COMPANY TO FULFILL THE PERFORMANCE BOND REQUIREMENTS OF THE CONSTRUCTION
CONTRACT BETWEEN LEGENDS LANDSCAPE, LLC AND THE CITY OF HUNTSVILLE ON SAFE
ROUTES TO SCHOOL (SRTS) PROJECT 09-01-01, AWARDING THE CONSTRUCTION CONTRACT
TO ENCINO LANDSCAPE, LLC TO COMPLETE THE SRTS PROJECT CONSTRUCTION, ADOPTING
ORDINANCE 2015-02 FOR THE BUDGET AMENDMENT FOR THE SAME,AND SUSPENDING THE
RULES OF PROCEDURE REQUIRING A SECOND READING.
WHEREAS The City of Huntsville,Texas awarded a construction contract on May 21,2013 for the Safe
Routes to School Project to a contractor who ultimately defaulted on said construction contract,and
WHEREAS By defaulting on the construction contract, the contractor has left sections of sidewalk
incomplete and in some cases in*need of repair and/or additional work and the City has worked with the
bond company to ensure completion of the project,and
WHEREAS The City of Huntsville wishes to enter into a Tender Agreement with Continental Casualty
Company to complete the Safe Routes to School Project construction;and
WHEREAS The original purpose of the Safe Routes to School Project was to ensure safe pedestrian
routes for children in Huntsville;and
WHEREAS The October 21, 2014 meeting of the City of Huntsville City Council will be used for the
purpose of providing the annual State of the City Address and such has been publicly announced;and
WHEREAS October 14, 2014 is being used to conduct the regular and routine business of the City
Council that would have otherwise occurred on October 21,2014 and this has been publicly announced;
and
WHEREAS The City Council wishes to award a construction contract to Encino Landscaping to ensure
completion of the Safe Routes to School Project;and
WHEREAS The City Council wishes to waive Section 3.05 of its Rules of Procedure to ensure a timely
award of construction and timely completion by Encino Landscaping.
NOW,THEREFORE,be It resolved by the City Council of the City of Huntsville,Texas,that:
Section 1: The above findings of fact are adopted by the City Council.
Section 2: The City Manager is hereby authorized to enter into a Tender Agreement with Continental
Casualty Company and receive a sum of $502,818.50 to complete the Safe Routes to School
Construction contract.
Section 3: The City Manager is hereby authorized to award a construction contract to Encino
Landscaping in the amount of$990,790 to complete the Safe Routes to School project.
Section 4: October 14,2014 is a regular meeting of the City Council in place of October 21,2014.
Section 5: Section 3.05 of the Rules of Procedure is waived by the requisite two-thirds vote of the City
Council.
Section 6: Ordinance No.2015-02,attachment#1, is hereby approved.
PASSED AND APPROVED this 14'h day of October 2014.
THE CITY OF HUNTSVILLE,TEXAS
141,
Mac Woodward, Vayor
ATTEST: APPROVED AS TO FORM:
4Lewar ,City LSecret-a-r-r—D ('/ and Schneider,City Attorney
ORDINANCE NO.2015-02
AN ORDINANCE OF THE CITY OF HUNTSVILLE, TEXAS, AMENDING THE 2014-2015
ANNUAL BUDGET AND CAPITAL IMPROVEMENTS PROJECTS (CIP) BUDGETS,
ORDINANCE NO. 201442 TO AMEND ADOPTED EXPENDITURES OF THE BUDGET;
AND DECLARING AN EFFECTIVE DATE.
WHEREAS, the 2014-2015 Annual Budget and CIP Budgets were adopted by Ordinance 201442 on
September 16,2014;
WHEREAS, various unforeseen circumstances affecting the City have presented themselves during the course
of the fiscal year;
WHEREAS, the City Council considered the circumstances independently, deliberating appropriately on the
associated revenues and expenditures and the overall impact on the general financial status of the City;
WHEREAS, pursuant to the laws of the State of Texas and the City Charter of the City of Huntsville, Texas,the
City Council has determined that it will be beneficial and advantageous to the citizens of the City of Huntsville
to amend the Capital Improvements Projects(CIP)budget as set forth herein;and
WHEREAS,this ordinance combines the independent Council actions into one budget amendment document;
NOW,THEREFORE,BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF HUNTSVILLE,
TEXAS,that:
Section 1. The findings set forth above are incorporated into the body of this ordinance.
Section 2. The Capital Improvements Projects budget is hereby amended to include the expenditures described
in Exhibit"A"attached hereto and made a part of this ordinance as if set out verbatim herein.
Section 3. All ordinances of the City in conflict with the provisions of this ordinance are hereby repealed, and
all other ordinances of the City not in conflict with the provisions of this ordinance shall remain in full force and
effect.
Section 4. Should any section, portion, sentence, clause or phrase of this ordinance be declared unconstitutional
or invalid for any reason, it shall not invalidate or impair the force or effect of any other section or portion of this
ordinance.
Section S. The necessity for amending the budget for the Capital Improvements Projects,as required by the laws
of the State of Texas, requires that this ordinance shall take effect immediately from and after its passage,as the
law in such cases provides.
Section 6.This ordinance shall take effect immediately after its passage.
PASSED AND APPROVED on this the 14 h day of October 2014.
THE CITY OF HUNTSVILLE TEXAS
14�4� L7
M c Woodward, Mayor
A' T ST: APP V D AS TO FORM:
r
Lee odward, e r Schneider, City Attorney
CTP Budget Amendments FY 14-15
October 10, 2014
a. Source: funds from default contractor's Bonding company(CNA $502,818.50
Surety)
Increase: Safe Routes to Schools Sidewalks Project $502,818.50
The original contractor on the Safe Routes to Schools Sidewalk project
defaulted and the Surety(Continental Casualty Company)for the default
contractor is required to ensure completion of the project and/or cover
any costs beyond the original contract amount and liquidated damages
(for going over the original contract period). The contract amount bid by
Explanation: the Completion Contractor(construction company hired to complete
remainder of the project)exceeds the balance of the original contract by
$408,973.50. Liquidated damages amounted to$93,845. This budget
amendment i
IIS s to increase the project budget by the amount that is being
paid by CNA Surety to the covering increased cost in completion of the
project and liquidated damages.